Use
Dependencies are defined for various assemblies in the BOM for material E-1000. Depending on the characteristic valuation, the assemblies required for the desired elevator variant are selected. In the same way, dependencies are defined for particular activities for standard network E-1000.
Procedure
Displaying Dependencies in the Material BOM
Menu Path |
Logistics ® Production ® Master Data ® Bills of Material ® Bill of Material ® Material BOM ® Display |
Transaction Code |
CS03 |
Field |
Data |
Description |
Material |
E-1000 |
|
Plant |
1300 |
Frankfurt |
Usage |
1 |
Production |
You can see that the object dependency indicator (OD) is set for a number of items.
You now see the dependency that has been maintained for this object.

The assembly E-1500 is selected only for elevator variants with 50kW motors.
Displaying Dependencies in the Standard Network
Menu Path |
Logistics ® Project System ® Basic Data ® Standard Templates ® Standard Network ® Display |
Transaction Code |
CN03 |
Field |
Data |
Standard Network |
E-1000 |
Alternative |
1 |
The system displays the dependency for activity 1040.
Dependencies are maintained for activities 1040 and 1090.
The selection condition ELEV_S_ACTIVITIES_IF_GLASS is assigned to the activities, along with the dependency CABIN_WALLS EQ ‘GLASS’.
The activities are only to be carried out if the cabin walls are made of glass. If you choose Wood panels for the cabin walls in the sales order, the activities are not adopted in the network.