Displaying Dependencies 

Use

Dependencies are defined for various assemblies in the BOM for material E-1000. Depending on the characteristic valuation, the assemblies required for the desired elevator variant are selected. In the same way, dependencies are defined for particular activities for standard network E-1000.

Procedure

Displaying Dependencies in the Material BOM

  1. Call up the transaction as follows:
  2. Menu Path

    Logistics ® Production ® Master Data ® Bills of Material ® Bill of Material ® Material BOM ® Display

    Transaction Code

    CS03

  3. Enter the following data:
  4. Field

    Data

    Description

    Material

    E-1000

     

    Plant

    1300

    Frankfurt

    Usage

    1

    Production

  5. Choose .
  6. You can see that the object dependency indicator (OD) is set for a number of items.

  7. Select the BOM item for component E-1500.
  8. Choose .
  9. Choose Dependency editor.
  10. You now see the dependency that has been maintained for this object.

    The assembly E-1500 is selected only for elevator variants with 50kW motors.

  11. Choose until the overview tree appears.

Displaying Dependencies in the Standard Network

  1. Call up the transaction as follows:
  2. Menu Path

    Logistics ® Project System ® Basic Data ® Standard Templates ® Standard Network ® Display

    Transaction Code

    CN03

  3. Enter the following data:
  4. Field

    Data

    Standard Network

    E-1000

    Alternative

    1

  5. Choose .
  6. Select activities 1040 and 1090, then choose Extras ® Object dependencies ® Editor.
  7. The system displays the dependency for activity 1040.

  8. Choose .
  9. To display the dependency for activity 1090, choose Yes.
  10. Choose Dependency editor.
  11. Dependencies are maintained for activities 1040 and 1090.

    The selection condition ELEV_S_ACTIVITIES_IF_GLASS is assigned to the activities, along with the dependency CABIN_WALLS EQ ‘GLASS’.

    The activities are only to be carried out if the cabin walls are made of glass. If you choose Wood panels for the cabin walls in the sales order, the activities are not adopted in the network.

  12. Choose until the overview tree appears.