Usage
You have already planned costs for the created activities by using the quantity structure for your turbine project. This quantity structure was costed automatically when you saved the project. Use the project planning board to find the origin of the activity costs.
Procedure
The project planning board appears. On the left, the system displays the structure and the selected data, on the right the scheduling data.
The system displays the activities costs aggregated for the activities (in other words, the highest WBS element shows the planned costs for the overall project).
Controlling costing
You now see the header data of the network.
Costing variants are stored for the network costing in Planned (CstgVariantPlan PS02) and Actual (CstVariantActl PS03). The Plan cost calc. indicator defines that the costs are costed automatically when saved.
Costs for internal processing activities
Activity 1000 is an internal processing activity.
Look at the fields that have a direct affect on costing:
The overhead rates and the planned costs from the internal activity are planned in the activity.
Costs for external processing activity
Activity 1300 is an external processing activity.
Look at the fields that have a direct affect on costing:
The Res./Purc.req. indicator defines that the system generates the purchase requisitions for the activity on release.
The overhead rates and the planned costs from external procurement are planned in the activity.
Costs for the general costs activity
This is a general costs activity. The planned costs are stored directly in the Amount field. On the tab page, look at the fields that have a direct affect on costing: