Usage
The processing of several activities in your turbine project T-10### is complete, and you now confirm the activities. An efficient way to do so is to enter confirmation in the PS Information System (Structure/Dates). There you can evaluate the data (actual dates, actual costs) entered immediately.
Prerequisites
You have transferred the additional functions
and
Confirmation via
to the standard toolbar.
Procedure
Menu Path |
Logistics ® Project System ® Information System ® Structures ® Structure Overview |
Transaction Code |
CN41 |
Field |
Data |
Project |
T-10### |
Additional selection criteria |
Delete |
Field |
Data |
Network |
First network of your project T-10### |
The system selects all activities that meet the filter requirements. The structure overview also displays the hierarchy upwards, and the components.

For the sake of simplicity, use today's date for the confirmation, as real dates are not relevant for this example. In a real situation, you might expect cost changes due to price markups if there were, for example, time delays.
The structure overview appears.
Result
The confirmation resulted in the actual dates and actual costs for the network activities being updated. The actual costs are displayed in aggregated form for the WBS elements.
A billing milestone is assigned to activity 5000. Once you have confirmed the activity, the milestone is exploded and this unlocks the billing date in the sales order.