The reorder level is defined as the sum of the safety stock plus the requirement forecast within the replenishment lead time (see formula (17)).

A forecast was carried out on a monthly basis. A month has 30 days in the case of external procurement.
Safety stock |
100 | |
Forecast |
1st subsequent period |
200 |
|
2nd subsequent periode |
00 | |
|
3rd subsequent period |
400 | |
Replenishment lead time |
40 days |
0/30 |
|
30/30 + 10/30 |
(an entire monthly requirement + a part of the the following month)
Reorder level = 100 + 30/30 * 200 + 10/30 * 300 = 400