Releasing the Project 

Use

You release the whole project.

Procedure

  1. Call up the transaction as follows:
  2. Menu Path

    Logistics ® Project System ® Project ® Special Maintenance Functions ® Work Breakdown Structure ® Change

    Transaction Code

    CJ02

  3. Enter the following data:
  4. Field

    Data

    Project def.

    E-#### (#### is the number of the sales order)

  5. Choose .
  6. Select WBS element E-####.
  7. Choose Edit ® Status ® Release.
  8. To check the release of a WBS element, select the WBS element, then choose Edit ® Status ® System/User status.
  9. On the Status tab page, you see that system status REL is active. On the Business transactions tab, you see a list of the business transactions allowed or prohibited for the active status.

  10. Choose .
  11. Choose .
  12. Choose until the overview tree appears.

Result

The system has now released the production order.

The system status is effective for all lower-level objects within the hierarchy of the work breakdown structure.