Planned Results Analysis
Use
You can use planned results analysis to calculate planned results analysis data for the following purposes:
Integration
This type of planned results analysis can only be used for projects and internal orders.
Planned results analysis is not appropriate for sales order items because the system must access periodic planned data, and such data is not available for sales order items. Planned results analysis is therefore not applicable to Product Cost by Sales Order.
Prerequisites
If you want to calculate planned results analysis data, you must have period-specific planning data.
For planned results analysis with internal orders, you can make the necessary settings in Customizing for Controlling ® Product Cost Controlling ® Cost Object Controlling ® Product Cost by Sales Order ® Period-End Closing ® Results Analysis in the steps Define Results Analysis Versions and Define Valuation Methods for Results Analysis.
For planned results analysis with projects, go into Customizing for the Project System under Revenues and Earnings ® Automatic and Periodic Allocations ® Results Analysis ®
Edit Results Analysis Keys and Version ® Maintain Results Analysis Versions.Proceed as follows:

The Actual and plan RA indicator also includes the functionality of the Simulate actual w/ plan indicator. If you have not yet calculated any results analysis data with the Simulate actual w/ plan indicator, then you should always calculate the planned results analysis data with the Actual and plan RA indicator. For information on the indicators, use the F1 help function.
Then go into Customizing for Product Cost by Sales Order under Period-End Closing ® Results Analysis in the step Define Valuation Methods for Results Analysis. Proceed as follows:
Features
If the Actual and plan RA indicator is set, two different types of results analysis data are generated:
results analysis process performed on the basis of the settings made for actual results analysis.<DS:DE.KKA_VERW_A>Istergebnisermittlung This means that to calculate the planned results analysis data, the system accesses the same Customizing settings as with the calculation of actual results analysis data.

Constraints: If the results analysis version is defined as the version relevant to settlement for planned settlement in Customizing for results analysis in the results analysis version, the plan version entered here must have the same number as the results analysis version used for planned results analysis.
Planned results analysis data cannot be transferred to Financial Accounting (FI).
The planned results analysis data is updated under a separate value type.
Activities
If you want to generate planned results analysis data, you must set the indicator planned results analysis before performing results analysis in the application.
See also:
Performing Results Analysis