Copying Component Data 
Use
Use this procedure to copy the General data and the Purchasing data from one component to another in the same network.
Prerequisites
You are the component overview for an activity or on a component detail screen.
Procedure
If you are on the component overview, select the components whose data you want to copy. on the component detail screen start at step 2.
Choose
.
The Copy component data dialog screen appears. On the left is the permissible source data and on the right the possible target components.
If necessary, change the data that is to be copied, or cancel the indicator for data that you do not to copy.
Select the required target components and choose
.
Result
After the following checks, the data is copied to the target components:
- If the requirements date is changed, the system sets the Man. requirements date indicator

Manual requirements dates are not adjusted if dates change.
- The system only copies the material group, if the target component does not have a material number
- The system only copies purchasing data for externally procured components
- The system only copies the account number of the vendor, if the target component does not have a purchasing info record.