Executing Scheduling in Monitoring Dates 
Prerequisites
You have created one or more groups for the current project. You have assigned events and components to these groups. You have specified the order in which the events occur and the time offset between consecutive events. See
Assigning Events to a Group and Assigning Components to a Group.Procedure
Dates
To select a component, select the row in which the name of the component and the traffic light appears . You cannot select individual date types on the date overview.
Scheduling. On the dialog box that appears you can select the date types to schedule, the scheduling direction and the events to schedule. If you select the Display parameters indicator, the dialog box appears every time you schedule.
You can schedule baseline dates and planned dates.
to schedule. Fixing Dates
It is possible to fix dates. A fixed date is not scheduled, irrespective of the scheduling parameters. To fix a date, go to the detail screen for a component, by selecting the component and choosing
. Set the Fixed indicator for the relevant event and date type.
Working with Scheduling Scenarios
You can reduce the amount of work involved in assigning and scheduling events by using scheduling scenarios. For more details, see
Scheduling Scenarios.Result
The system schedules the selected dates and events in the selected direction. The results are displayed immediately in the dates overview.