Displaying and Creating Dates 

Displaying and Creating Order Dates

  1. Choose Logistics ® Plant maintenance ® Maintenance processing ® Order ® Change.
  2. Enter the order number and choose Continue.

The header data screen for the order appears.

  1. To display the basic dates calculated, those already entered by you and the actual dates for the order, choose Display other scheduling data.
  2. Enter the missing order dates as parameters for scheduling the operations.

If you have selected a scheduling type using time of day, the system likewise calculates the second basic date using time of day.

The system schedules automatically when an order is saved. However, you can also schedule the order before it is saved.

Displaying Operation Dates

  1. Choose Logistics ® Plant maintenance ® Maintenance processing ® Order ® Change.
  2. Enter the order number and choose Continue.
  3. The header data screen for the order appears.

  4. Select the operation overview of the required order.
  5. Select the operation for which you want to display the scheduling data.
  6. Then select the pushbutton Dates.

The Operation Dates screen appears containing the dates and times calculated for the selected operation.

Displaying the Scheduling Overview as a Graphic

  1. You have the following initial entry options:
  1. Enter the required selection data and choose Execute.
  2. Select the lines containing the orders or operations, for which you want to display a scheduling overview. Keep the CTRL button held down for this.
  3. Choose Goto ® Scheduling overview.
  4. The system displays the graphical scheduling overview.

  5. Return to the list using Graphic ® Exit.