Displaying, Changing and Deleting Relationships 

Displaying Relationships

  1. Call up the order in change mode.
  2. Select the operation overview.
  3. Then call up the relationships overview as a graphic using Goto ® Graphics ® Network structure or as a list using General ® Relationships.

Changing Relationships

Before making any changes to relationships, you should consider whether the changes are really necessary, since they may affect the scheduling of the whole order.

  1. Call up the order in change mode.
  2. Choose the operation overview and call up the graphic using Goto ® Graphic ® Network structure.
  3. Select the relationship and choose Relationship.
  4. Enter the changes, choose Continue and return to the operation overview.
  5. Save the order.

Deleting Relationships

If you delete the relationships in an order, the operations affected are removed from the network structure. If you then schedule the order, the system assumes that these operations start at the same time, independent of one another.

If you delete a relationship, you change the network structure. Before you delete relationships, you should therefore make sure that execution of the order has not yet begun.

  1. Call up the order in change mode.
  2. Call up the operation overview of the order and select the operation for which you want to delete a relationship.
  3. Call up either the graphic using Goto ® Graphic ® Network structure or the list of relationships using General ® Relationships.
  4. Select the relationship you want to delete and choose Delete.
  5. Once all the relationships have been deleted, the system automatically adjusts the scheduling for the order. The system informs you of the change in an online message.

  6. Save the order.