Generate Pool of Confirmations
Use
Employees responsible for procurement enter the work they have done in timesheets. The employee takes the activities to be confirmed from the pool of confirmations produced in the project information system
Procedure
Menu Path |
Logistics or Accounting ® Project System ® Information System ® Structures ® Structure Overview |
Transaction Code |
CN41 |
The Project Info System: Structure Initial Screen appears.
Field |
Data |
Project |
E-# # # # |
Additional selection criteria |
Delete |

If the icon does not appear in the menu bar, adapt your
application function bar .Field |
Data |
Work center (Frm) |
2300 |
Field |
Data |
Confirmation pool |
E-####-PROC |
Description |
Procurement |
Entering Working Times
Use
In this step, you adopt the default values from the worklist, without changes, as the work time you want to enter. There is no need to release or approve the times entered.
Procedure
Menu Path |
Logistics ® Project System ® Progress ® Confirmation ® Time Sheet ® Time Data ® Enter |
Transaction Code |
CAT2 |
Field |
Data |
Data entry profile |
13000000 |
Personnel number |
1255 |
Data entry profile 1300000 determines the process for entering data and how the time sheet appears for confirming the process. For example, it determines which data can be maintained.
Field |
Data |
Key date |
Today’s date |
Confirmation pool |
E-####-PROC |
The Time Sheet: Data Entry View is divided into the following areas:
You can scroll through the calendar to scroll into the past or future. Use the scroll keys next to the fields in the data entry fields to do this.
The system copies the activities and work times for the data entry period to the data entry part.

Depending on the schedule situation in the network, the procurement activities are distributed over two or three weeks.
Transferring Work Times to the Project System
Use
The times entered are saved in the work sheet. As the current profile settings mean that the work times entered are not to be approved or released, you can transfer the data to the Project System in the very next step.
Transferring the data to the Project System automatically confirms the procurement activities. The system also transfer the work times reported to Human Resources.
Procedure
Menu Path |
From the Time Sheet node, choose Transfer ® Project System ® Transfer. |
Transaction Code |
CAT5 |
Field |
Data |
Personnel number |
1255 |
Posting date |
Today’s date |
Log |
Select |
Test run |
Deselect |
The transfer program outputs a detailed log of the confirmations transferred. A confirmation document is created for each day.