Use
You copy the components to be delivered from the Project System to the Sales and Distribution system for further processing.
Procedure
Menu Path |
Logistics ® Project System ® Material ® Execution ® Delivery from Project |
Transaction Code |
CNS0 |
Field |
Data |
Shipping point |
1300 |
Plan Gds Mvm |
Today’s date |
Ship-to party |
1600 |
Sales org. |
1000 |
Distribution channel |
10 |
Division |
00 |
The screen shows all the delivery-relevant material components in the project, with the requirements dates from network scheduling.
In the current network, these are the dates as of which the material components are to be available for delivery. Deliveries can be assembly in line with the requirements dates.
As you chose today's date for the goods issue, only the components already in stock can be delivered. The system sets the delivery quantity in the appropriate delivery items to the same level as the requirements quantity (default value),
The delivery and requirements quantities are now the same in all the items in the Delivery from Project: Process Delivery Items screen.
The system confirms the posting and displays a number. Make a note of this number.