Confirming the Production Order 
Use
The production of the cabin and motor is represented in simplified form in this process because the integration of the Project System with production but not with the processes within production is to be represented.
The system automatically posts the following when an order is finally confirmed:
Prerequisites
To be able to post all goods movements in the procurement phase, you must release the WBS elements to which assignments are to be made.
In this example, E-####-2 is the top WBS element in the procurement subhierarchy. The lower-level WBS elements are the account assignment elements for the procurement activities in the network.
Procedure
Menu Path |
Logistics ® Production ® Production Control ® Confirmation ® Enter ® For Order |
Transaction Code |
CO15 |
Field |
Data |
Order |
The number of one of your production orders |
Field |
Data |
Final conf. |
Select |
Yield to Conf. |
1 |
Un. |
PC |
Result
Final confirmation with quantity of one piece has been entered for the production order. The system simultaneously posted the material to project stock.