Confirming the Production Order 

Use

The production of the cabin and motor is represented in simplified form in this process because the integration of the Project System with production but not with the processes within production is to be represented.

The system automatically posts the following when an order is finally confirmed:

Prerequisites

To be able to post all goods movements in the procurement phase, you must release the WBS elements to which assignments are to be made.

In this example, E-####-2 is the top WBS element in the procurement subhierarchy. The lower-level WBS elements are the account assignment elements for the procurement activities in the network.

Procedure

  1. Call up the transaction as follows:
  2. Menu Path

    Logistics ® Production ® Production Control ® Confirmation ® Enter ® For Order

    Transaction Code

    CO15

  3. Enter the following data:
  4. Field

    Data

    Order

    The number of one of your production orders

  5. Choose .
  6. Enter the following data:
  7. Field

    Data

    Final conf.

    Select

    Yield to Conf.

    1

    Un.

    PC

  8. Choose .
  9. Repeat steps 2 to 5 for the second production order.
  10. Choose .

Result

Final confirmation with quantity of one piece has been entered for the production order. The system simultaneously posted the material to project stock.