Standard Work Breakdown Structure 
Menu Path |
Logistics ® Project System ® Basic Data ® Standard Templates ® Standard WBS ® Display |
Transaction Code |
CJ93 |
Field |
Data |
Std Project Def. |
E-1000 |
You now see all of the WBS elements contained in the standard WBS.
The graphic illustrates the work breakdown structure.


The operative indicators tell you which tasks the individual WBS elements perform during project execution. For example, WBS element E-1000 is the billing element.