Use
Confirmations document the state of processing for activities and activity elements in the network and provide a forecast of how processing will proceed further.
The activities "Layout" and "Customer Acceptance" have already reached the milestone that releases them for processing. You use the Project Builder to confirm activity processing as complete.
Procedure
Menu Path |
Logistics ® Project System ® Project ® Project Builder |
Transaction Code |
CJ20N |
The Project Builder screen appears.
The Open Project dialog box appears.

If the system does not display all icons in the Structure Tree screen area, you can enlarge the screen area or choose Expand all using the right mouse button.
A dialog box appears, showing the actual data for activity 1000 Layout. The final confirmation indicator is set.
.The Project Builder screen appears.
The dialog box for activity 1010 Customer Acceptance appears.
The dialog box Milestone Functions appears, showing information on the release of activities directly following this one.
In the Customer Acceptance milestone, the Release of Directly Following Activities is maintained in the Confirmed status. This status is set when you set the final confirmation indicator for the activity. Doing this triggers the milestone function.
The design activities directly following this one are automatically released for processing.
The Project Builder screen appears.