Displaying Project Data 

Use

Use the evaluation options provided by the project information system to view the project generated as a result of your configuration entries:

· Structure Overview

· Project structure graphic

· Gantt Chart

Procedure

  1. Call up the transaction as follows:
  2. Menu Path

    Logistics ® Project System ® Information System ® Structures ® Structure Overview

    Transaction Code

    CN41

  3. If required, specify PS info profile 000000000001 , then choose .
  4. Enter the following data:
  5. Field

    Data

    Project

    E-#### (#### is the number of the sales order)

    Additional selection criteria

    Delete

  6. Choose .
  7. The structure overview shows the project objects as they appear in the project hierarchy. You can branch from the structure overview to individual overviews, detail screens, and graphical evaluations.

  8. Select E-#### and choose .
  9. Choose .
  10. All the objects in the structure are selected.

  11. Choose Graphic ® Project Structure.
  12. The project structure graphic gives you an overview of how the project is set up, of the dates in the project, and of the different WBS element types and activity types and how they are used.

  13. Choose Settings ® Legend ® Left.
  14. The legend now shown on the left-hand side of the display area supplies information on the graphical elements and the data shown.

  15. Choose WBS Elements.
  16. The Node Representation: WBS Elements dialog box appears.

  17. Select Expanded and choose .
  18. Choose Activities.
  19. Select Expanded and choose .

The extended node representation is the most detailed form of display.

  1. Choose .
  2. The structure overview appears.

  3. Choose Graphic ® Gantt Chart.
  4. The bar chart gives you a graphical overview of the whole project. The overview is similar to the Gantt chart, but has more functions.

    In addition to time planning, you can access, amount other things, detail screens for activities, relationships, and milestones, and insert additional fields to display planned and actual costs in the table area.

  5. Select the network header Elevator Model 1000, then choose .

This takes you the Project Information System: Network Detail Screen dialog box.

Make a note of the network number. You will need it later.

  1. Choose .
  2. Choose until the overview tree appears.