Confirming Activity 

Procedure

  1. Call up the transaction as follows:
  2. Menu Path

    Logistics ® Project System ® Progress ® Confirmation ® Individual Confirmation ® Enter

    Transaction Code

    CN25

    You reach the Create Network Confirmation: Initial Screen.

  3. Enter the following data:
  4. Field

    Data

    Network

    Network number proposed by the R/3 System

    Activity

    2000

  5. Choose .
  6. The R/3 System branches to the Create Network Confirmation: Actual data screen.

  7. Enter a duration of 3 days.
  8. Choose .
  9. On the Create Network Confirmation: Initial Screen, the R/3 System informs you that the confirmation has been saved.

  10. Choose until the overview tree appears.