Aligning Activity Duration with Material Lead Time 
Use
You can adjust the duration of a network activity to match with the lead times of all the material components assigned to it.
Prerequisites
You are on the
component overview for the activity.When calculating the overall lead time, the system only considers those material components for which you have set the indicator Align.Fin.date on the component detail screen.
Procedure
On the component overview for the activity, select those components whose lead times should determine the activity duration.
By double-clicking on the component in the component overview call up the detail screen and set the Align. Fin.date indicator. Return to the component overview.
Choose Component
®
Duration deliv. timeSave the network.
Result
The system determines the whole procurement lead time and the maximum duration of the activity from the following factors.
- The planned delivery time of externally procured material components
- Total replenishment lead time for internally produced components or the in-house production time, if the total replenishment lead time has not been entered on the relevant MRP tab page.