Exploding the Bill of Material 
Use
If you have allocated a material with a bill of material (BOM), a sales order BOM, or a WBS BOM to an activity, you can explode this BOM in the network level-by-level or completely (multi-level).
You need to explode a bill of material, if
For more information, see
BOM Explosion
If the material component was already allocated to the activity before the BOM explosion, you have the following options.
Procedure
The BOM selection dialog box appears.
Execution Factor in the activity. You can explode the BOM level-by-level or all at once (multi-level).

If you explode the BOM all at once, requirements could be generated both in the network and in MRP, depending on control of the BOM items. Since MRP always explodes the complete BOM, this could lead to multiple requirements for the same component.
A list of all the BOM items appears. You expand or compress multi-level BOMs by choosing
or
. Choose
to display the BOM as an overview tree of the BOM structure in which phantom assemblies are shown as such.

Document items are not displayed, since the system does not copy document items to network activities.
See also:
BOM transfer