Budget Management
The budget is the approved cost structure for a project.
It differs from project cost planning in that it is binding. While you must estimate costs as accurately as possible during the planning phase, it is in the approval phase that you prescribe your project funds, in the form of a budget. The budget is the device by which the management approves the expected development of project costs over a given timeframe.

The Project System recognizes the following different budget types:
Original budget
+ Supplements
- Returns
+/- Transfers
= Current budget
This section describes:
allocate the original budget in a project
budget updates in the form of supplements, returns, and transfers
release the budget