Adjusting Plan Values 

Use

You can adjust the plan values in a project or in selected WBS elements - that is, you can increase or decrease them by a particular percentage or amount.

Procedure

  1. In the WBS element overview in cost planning, select the WBS elements whose values you want to adjust.
  2. Choose Edit ® Adjust.
  3. The Adjustment dialog box appears.

  4. Enter the percentage or amount by which you want to change the plan value.
  5. If you want to reduce the plan value, enter a minus sign ("-") after the figure.

  6. Choose .
  7. The system updates the plan values per your input.

  8. Choose Save.