Displaying Plan Costs for Orders for Projects in the Cost Information System 

The table below illustrates how the costs for a WBS element are represented in the cost information system. The plan costs and assigned values for the WBS element change, depending on what you have entered in the Project System implementation guide. In the example, the WBS element already has a planned value of $100,000 and an assigned value of $30,000.

Representation in the Cost Information System

Plan Value

The order

Representation in Information System

 

Order ($)

is:

For plan

and Assigned ($)

20 000,-

Appended

120 000,-

30 000,-

     

Not apportioned

20 000,-

Not appended

100 000,-

30 000,-

     

Not apportioned

20 000,-

Appended

120 000,-

50 000,-

     

Apportioned

20 000,-

Not appended

100 000,-

50 000,-

     

Apportioned

The project summarization only takes account of plan costs in appended orders.