Displaying Plan Costs for Orders for Projects in the Cost Information System 
The table below illustrates how the costs for a WBS element are represented in the cost information system. The plan costs and assigned values for the WBS element change, depending on what you have entered in the Project System implementation guide. In the example, the WBS element already has a planned value of $100,000 and an assigned value of $30,000.
Representation in the Cost Information System
Plan Value |
The order |
Representation in Information System |
|
Order ($) |
is: |
For plan |
and Assigned ($) |
20 000,- |
Appended |
120 000,- |
30 000,- |
|
Not apportioned | |||
20 000,- |
Not appended |
100 000,- |
30 000,- |
|
Not apportioned | |||
20 000,- |
Appended |
120 000,- |
50 000,- |
|
Apportioned | |||
20 000,- |
Not appended |
100 000,- |
50 000,- |
|
Apportioned |

The project summarization only takes account of plan costs in appended orders.