Dates in Milestones 

Features

You can maintain basic dates and forecast dates for milestones. The following is an overview of dates that you can define for milestones

Actual dates

Actual dates can be either:

The confirmed actual date is the default value, however, you can overwrite it.

Fixed Dates

A fixed date is a manually entered finish date on which the milestone should be reached.

To be able to use the milestone technique for WBS elements in earned value analysis, you must use fixed dates for the milestone.

Dates

As an alternative to fixed dates, you can also specify the following for a milestone:

The activity has a duration of 50 days and an offset of 20% to the start. The milestone date is 10 days after the activity start.

Scheduled Dates

Scheduling calculates the scheduled dates in the following manner: