If you create a (standard) network and assign it to a WBS element in the header, the system copies that WBS element into all activities and activity elements as a default value.
You can assign the activities to different WBS elements by selecting the menu options Goto
®
WBS assign.-activity.
You can assign activity elements to different WBS elements by selecting the menu options Activity
®
WBS assign.-element.