Activity Data 

Work

For internally processed activities you determine how much work is needed to conduct the activity, which capacities are required and which qualifications the personnel should have.

See also :

Work

External processing

Activities and activity elements can also be performed outside of your company. The system takes the data in the activity and creates a purchase requisition which is processed by the purchasing department.

See also :

External processing

Material

You can allocate materials to all activities in standard networks and networks.

Production Resources/Tools (PRT)

You can assign production resources/tools (PRT) to each activty Unlike machines and fixed assets, production resources/tools (PRTs) are movable (non-stationary) operating resources, that are required to perform an activity and can be used repeatedly.

Documents

There are several ways to assign a document to an activity.

Classification

You can use the SAP Class System to classify activities. Within the Class System you can determine the values that are used to valuate an activity. Classification is also used for cost summarization.

When you create a network by copying from a standard network with classification attributes, the classification attributes are not copied. They are only used for classifying the standard network.

Organizational Data in Activities

The following is valid for activity organizational data :