Displaying Revenues 

Use

The report Revenues: Planned Contribution Margin displays the revenues according to the billing plan. The down payment requests do not affect revenues. The first revenues are recorded only when this first partial invoice is made.

Procedure

  1. Call up the transaction as follows:
  2. Menu Path

    Logistics ® Project System ® Information System ® Financials ® Revenues and Earnings ® Hierarchical ® Planned Contribution Margin

    Transaction Code

    S_ALR_87013565

  3. In the dialog box, choose .
  4. If required, enter controlling area 2000 , then choose .
  5. If required, enter database profile ZECPP0000001 , then choose .
  6. Enter the following data:
  7. Field

    Data

    Project

    A-20###

    Additional selection criteria

    Delete

  8. Choose .
  9. Double-click project definition PRJ A-20###.

You see an overview of the planned values, displayed by individual years.