Use
You create a billing plan on the basis of milestones that have been defined for specific network activities of your project. The system determines the planned dates using the scheduled milestones.
You use a billing plan to plan for each order item:
If a milestone has been reached successfully, the customer is billed for a percentage of the total project costs.
When you confirm the billing milestone that exists in the project, this triggers a down payment request to the customer. Additional payment milestones generate partial or final payments.
The planned revenues are derived automatically from the billing plan and updated to the corresponding WBS elements.
Prerequisites
You have created a project with billing milestones and a sales order.
The sales order has been assigned to project.
You have indicated the WBS element on which you wish to plan the revenues as a billing element.
In Customizing of the Project System, we have defined that the system updates the billing data from a project-assigned sales order to the assigned WBS element.
Procedure
Menu Path |
From the Order node, choose Change |
Transaction Code |
VA02 |
Field |
Data |
Order |
Your sales order number |

To search for the document number of your order, you can use the PO number A-20###.
Field |
Data |
WBS element |
Select |
Field for WBS element |
A-20### |
The Select Milestones dialog box appears.
The system adopts the milestone dates as billing dates. The system issues a block to all of the billing dates. These blocks are only removed when you make the final confirmation for the milestone.
Field |
Data |
WBS element |
Select |
Field for WBS element |
A-20### |
Result
You used billing plans to plan the expected revenues of the document items of your sales order. These refer to the existing billing milestones contained in the project.
Your billing plan for document item IECPP-1-VE01 contains the following dates:
When you have confirmed the activity Follow-Up Assembly the customer is invoiced for 50% of the net value after confirmation of final acceptance of the remainder.
Your billing plan for document item IECPP-1-PP01 contains the following dates:
When you have confirmed the activity Foundations the customer is invoiced for 35% of the document item.
When you have confirmed the activity Follow-Up Assembly the customer is invoiced for 50% of the net value after confirmation of final acceptance of the remainder.