Use
To get as complete a view as possible of project costs at an early stage, you plan the material costs for components before they are assigned to activities.

The planned values are reduced after assigning the components. This avoids planning material costs twice.
In the meantime you have defined the project owner, to whom you assign all of the WBS elements through mass change.
Prerequisites
Your project T-10### is open in the project builder.
Procedure
Assignment of material planning values to activities

The activity number is in the last column (Identification).
Field |
Data |
Mat.planning |
100.000 |
Activity |
Field |
Data |
Materialbeschaffung für Fertigung (3100) |
Mat.planning |
150.000 |
Materialbeschaffung für Anlagenteile (3200) |
Mat.planning |
250.000 |
Assignment of a project owner using mass change
Field |
Data |
New value |
01 |
The system assigns all WBS elements from your project to 01 Andreas Fischer.