Planning Material Costs 

Use

To get as complete a view as possible of project costs at an early stage, you plan the material costs for components before they are assigned to activities.

The planned values are reduced after assigning the components. This avoids planning material costs twice.

In the meantime you have defined the project owner, to whom you assign all of the WBS elements through mass change.

Prerequisites

Your project T-10### is open in the project builder.

Procedure

Assignment of material planning values to activities

  1. Expand the Turbine ® Einkauf node.
  2. In the Structure tree area click on the activity Vorabbestellungen (3000).
  3. The activity number is in the last column (Identification).

  4. In the work area, select the Assignments tab page.
  5. Enter the following data:
  6. Field

    Data

    Mat.planning

    100.000

  7. Maintain the planning values for the following activities at the same time:
  8. Activity

    Field

    Data

    Materialbeschaffung für Fertigung (3100)

    Mat.planning

    150.000

    Materialbeschaffung für Anlagenteile (3200)

    Mat.planning

    250.000

  9. Choose .

Assignment of a project owner using mass change

  1. On the tool bar, choose .
  2. Choose the WBS elements tab page.
  3. Choose .
  4. Select Person responsible from the list on the right, and choose .
  5. Choose .
  6. Enter the following data:
  7. Field

    Data

    New value

    01

  8. Choose .
  9. The system assigns all WBS elements from your project to 01 Andreas Fischer.

  10. Choose .
  11. If a warning occurs, select .
  12. Choose .