Displaying a Scheduling Overview from the Maintenance Plan 

  1. In the maintenance planning menu, choose one of the following options:
  2. Maintenance plans ® Display

    Maintenance plans ® Change

    Scheduling ® Schedule

  3. Enter the number of the required maintenance plan and choose Continue.
  4. You reach the Maintenance Schedule screen.

  5. To display the graphical maintenance scheduling overview, choose Extras ® Maintenance item overview.

The system displays the graphical maintenance scheduling overview.

If you have called up the scheduling overview using Schedule or Change maintenance plan, you cannot make any changes.

If you display the graphical maintenance scheduling overview directly from the maintenance plan, you can make changes.

For more information, see Displaying a Graphical Scheduling Overview or Simulation Directly.

See also:

Working with the Graphical Scheduling Overview

Variant Maintenance for Scheduling Overview