The preliminary buffer specifies how long before the due date for the maintenance package the activities can be started, without the subsequent due dates being changed.

You specify a preliminary buffer of 5 days for each maintenance package in the strategy.
The planned date calculated by the system is September 30. The start date proposed in the maintenance order is therefore September 25.