Example of Maintenance Plan Costing
In this example, maintenance plan costing is performed for a one-year analysis period from 01.01 to 31.12. The strategy assigned to the maintenance plan contains two maintenance packages:
The following calculations take different
package hierarchies.Determination of the frequency for Calculation 1
Package 2 belongs to a higher hierarchy than package 1.
Package |
Due Date |
Frequency |
Special Features |
Package 1 |
1M |
8 times |
Packages 1 and 2 are due at the same time four times. Because only the packages with the higher hierarchy number are executed, package 1 is omitted when two packages are due at the same time. |
Package 2 |
3M |
4 times |
Determination of the frequency for Calculation 2
Package 1 and package 2 belong to the same hierarchy.
Package |
Due Date |
Frequency |
Special Features |
Package 1 |
1M |
12 times |
Packages 1 and 2 are due at the same time four times. The same package hierarchy means that both packages are always due. In this case, neither package is omitted when both packages are due at the same time. |
Package 2 |
3M |
4 times |
Determination of Costs