Creating a Single Cycle Plan 

  1. Choose Logistics ® Plant Maintenance ® Planned Maintenance ® Maintenance Planning ® Maintenance Plans ® Create ® Single Cycle Plan.
  2. You reach the screen for creating a maintenance plan.

  3. Enter the maintenance plan category and choose .
  4. You reach the initial screen for creating a single cycle plan.

  5. Enter the necessary data.
  6. If you specify a performance unit for the cycle, the system automatically selects the first counter suitable for the reference object as a default value.

  7. Maintain the scheduling parameters if necessary on the tab Maintenance plan scheduling parameters.
  8. You can only maintain the scheduling parameters for the maintenance plan if you have entered a unit in the section Interval for the cycle. From the unit, the system can recognize whether the single cycle plan is performance-based or time-based and provides the corresponding scheduling parameters.

  9. Enter the necessary data for the maintenance item.
  10. You assign a task list if necessary to the maintenance item:
  1. Assign further technical objects to the maintenance item if necessary using the tab Object list (see Object List).
  1. If you want to create further maintenance items, choose with quick info Create MaintItem.
  1. Save the maintenance plan.

See also

Profile for a General Maintenance Task List