Evaluating Costs in the Cost Element Report 
Usage
For project controlling, you evaluate the costs by cost element in the Project Information System.
Prerequisites
You update planned costs to your project.
Procedure
Menu Path |
From the Project System node, choose Information System ® Financials ® Execute Report ® Cost Element Report. |
Transaction Code |
GR55 |
Field |
Data |
Project |
T-10### |
Controlling area |
1000 |
Plan version |
0 |
From fiscal year |
Current year |
To fiscal year |
Current year + 2 |
From period |
1 |
To period |
12 |
Additional selection criteria |
Delete |
The aggregated costs of your project are displayed in the report.