Creating a New Quotation on the Basis of the Simulation Version 

Use

In this example, the customer decides that the technical statistics and performance of the generator should be changed. Efficiency and performance are to be increased and it therefore becomes necessary to manufacture this generator in-house.

A similar scenario has already been costed in simulation SIM20###, so it only remains to recalculate a new sales price. This time, however, on the basis of the simulation.

Prerequisites

See also:

Sales Pricing / Creating a Sales Quotation

Procedure

  1. Call up the transaction as follows:
  2. Menu Path

    Logistics ® Project System ® Financials ® Planning ® Sales Pricing

    Transaction Code

    DP81

  3. Enter the following data:
  4. Field

    Data

    Project definition

    A-20###

    Pricing date

    Today’s date

    Version

    SIM20###

  5. Choose Sales price.
  6. The sales price basis is converted to the order items. This takes place in accordance with the settings in the DIP profile.

  7. If you double-click on IECPP: Quotation, a pricing procedure that you can process appears in the lower part of the screen.
  8. Enter the following data for the risk and profit surcharge:
  9. CnTy

    Rate

    ZEC3 (IECPP: risk)

    5

    ZEC4 (IECPP: profit)

    3

  10. To create a quotation, choose Quotation.
  11. Choose Yes in the dialog box.
  12. Enter the following data:
  13. Field

    Data

    VPK short text

    Quotation 20### simulation

  14. Choose .
  15. The Change Quotation: Overview screen appears.

  16. Enter the following data for the submission deadline for the quotation on the Item overview tab page:
  17. Field

    Data

    Valid to

    Today’s date + 6 months

    Purch. order no.

    A-20###

  18. Choose .
  19. To confirm possible warning messages, choose .
  20. Note the number of the quotation.

Result

You have created a new quotation on the basis of the planning data for the simulation. You can send the new quotation to your customer.