Comparing the Operative Project With the Simulation 

Prerequisites

The PS information profile ZECPP0000001 and the status selection profile ZECPP01 (IECPP without deletion flag) have been defined in Customizing for Project System.

Procedure

  1. Call up the transaction as follows:
  2. Menu Path

    Logistics ® Project System ® Information System ® Structures ® Structure Overview

    Transaction Code

    CN41

  3. In the dialog box, enter the following data:
  4. Field

    Data

    PS Info Profile

    ZECPP0000001 (IECPP: dates and costs/versions)

  5. Choose .
  6. Enter the following data on the initial screen:
  7. Field

    Data

    WBS element

    A-20###-03-07

    Additional selection criteria

    Delete

    Current data

    Select

    Version data

    Select

    Structure-related

    Select

    Project version

    SIM20###

  8. Choose .

Result

You can see the comparison of costs for project A-20### and simulation SIM20###.

On the grounds of the cost situation, you choose the operative project – and therefore also external procurement of the generator.