Comparing the Operative Project With the Simulation 
Prerequisites
The PS information profile ZECPP0000001 and the status selection profile ZECPP01 (IECPP without deletion flag) have been defined in Customizing for Project System.
Procedure
Menu Path |
Logistics ® Project System ® Information System ® Structures ® Structure Overview |
Transaction Code |
CN41 |
Field |
Data |
PS Info Profile |
ZECPP0000001 (IECPP: dates and costs/versions) |
Field |
Data |
WBS element |
A-20###-03-07 |
Additional selection criteria |
Delete |
Current data |
Select |
Version data |
Select |
Structure-related |
Select |
Project version |
SIM20### |
Result
You can see the comparison of costs for project A-20### and simulation SIM20###.