In this step, you define:
of the determination of change texts
Text number
In the standard system supplied, the change text "Unit of measure changed" (text no. P5) is directly assigned to the base unit (MEINS field):
If the base unit is changed in an already printed RFQ, purchase order, or outline agreement, the change text "unit of measure changed" is included in the change notice (printout of changes).
Routine
In the standard system supplied, the deletion indicator (LOEKZ field) is assigned to routine 3 , which controls the outputting of the change text.
Routine 3 checks whether an item of a purchasing document has been deleted or blocked. If the item has been deleted, the change text "Item cancelled" (S3-L) is included in the printout of changes. If the item has been blocked, the change text "Item blocked" (S3-S) is printed.
SAP recommends working with the settings of the standard system. In this case, you need take no further action.
If you wish to define further fields as relevant to change notices, you must carry out the following activities:
Note
If you specify a text number and a routine, the routine will receive preferential treatment.