Displaying a Permit List 

  1. Depending on the application component in which you are working, choose one of the following menu paths:

A selection screen appears.

  1. Enter data as required.
  2. Specifying the duration until the key date is necessary for using the traffic light display in the results list to see how urgently which permits should be issued until this date.

  3. Choose Execute.

The list of permits appears.

The traffic light colors signify the following:

Traffic Light Color

Meaning

Green

The permit was issued on time.

Yellow

The permit has not yet been issued, although its issue is:

  • Necessary for release and the basic start date is not yet past and occurs before the key date
  • Recommended for release and the basic start date is before the key date
  • Necessary for completion and the basic end date is not yet past and occurs before the key date
  • Recommended for completion and the basic end date is before the key date

Red

The permit has not been issued, although its issue is:

  • Necessary for release and the basic start date is already past
  • Necessary for completion and the basic end date is already past

<None>

The permit does not need to be issued (yet).

  1. To display more detail data for the order to which a permit is assigned than just the order number, choose Display order.

 

For more information, see Entering, Issuing and Canceling a Permit.