Use
You have scheduled internal and external services for the activities in the network.
Taking the dates into account, the system calculates the planned costs using the valuation records or the prices for internal and external services and the required operating resources.
The time-based distribution of the planned costs is the result of the time-based distribution of the planned services and the operating resources for the individual activities.
The costs of the activities are assigned to the WBS elements by assigning the activities.
You can find further information in the SAP Library under Logistics ®
Project System ® Structures ® Project Planning Board and Logistics ® Project System ® Costs.Prerequisites
The controlling area must have been set to 2000. In a North American corporate group, cost accounting that takes place across different company codes is performed using the currency USD (U.S. dollars).
You are still in the Project Builder.
Procedure
.The Project Planning Board
screen appears.Result
The system has determined the planned project costs.