Installing Equipment 
Prerequisites
The master records for the functional location and the pieces of equipment must already be created in the system. You can install several pieces of equipment at the functional location.
Procedure
From the main menu, choose Logistics
®
Plant maintenance
®
Technical objects
®
FunctLocation
®
Change.
The screen Change Functional Location: Initial, is displayed.
Make all the necessary entries for the functional location in the initial screen and then choose either Goto
®
Location data or Goto
®
PM data.
The functions for installation/dismantling can be selected from either screen.
To do this, choose Structure
®
Equipment.
- If no pieces of equipment have yet been installed at the functional location, you go to the screen Installation Location: Install Equipment.
- If pieces of equipment have already been installed at the functional location, you go to the screen Installation Location: Equipment Overview, on which you see a list of all the pieces of equipment installed at this functional location.
Select Edit
®
Install equipment, to go to the screen Installation Location: Install Equipment.
For how to change the position number of the installed pieces of equipment, see
Changing the Position Number.
- Enter the pieces of equipment that you want to install at the functional location in the section Equipment.
- Now you can choose Extras
®
Change log to display:
- Which pieces of equipment are installed
- Which pieces of equipment were installed before this installation
- Which pieces of equipment are installed after this installation

If you want to use the Data transfer function for the newly installed pieces of equipment, proceed as described in
Data Transfer.
- Return to the Maintenance data or Location data screen and save the installation.