 Overdue Project Milestones

 

The analytical app displays the Key Performance Indicator (KPI) Overdue Project Milestones. You can display the milestones that are overdue across projects.

Key Features

  • Enables you to view the percentage of completion of a project milestone along with project details.

  • Displays the partial project hierarchy structure from the selected milestone up to the project definition.

  • Calculates the number of days by which a project milestone is overdue with reference to the basic scheduled date. In the absence of this, the calculation rule uses the basic fixed date.

  • You can group the milestones based on the project it belongs to or the days by which it is overdue.

  • You can filter the milestones based on any of the following:

    • Range of days overdue

    • Project

    • Usage Description

  • You can navigate to related transactional apps and fact sheets.

  • Integration with the SAP Jam collaboration platform.

Navigation Targets

The app offers the possibility to directly access other apps.

Note Note

These linked apps have to be already available in your system landscape or you have to implement them along with this app.

End of the note.
  • Confirm Project Milestone transactional app

  • Project fact sheet

  • WBS Element fact sheet

  • Network Activity fact sheet

System Landscape Requirements

The app consists of front-end components and back-end components. The back-end components and the front-end components are delivered in separate products and have to be installed in a system landscape that is enabled for SAP Fiori.

SAP Smart Business Product

SAP Smart Business 1.0 for SAP ERP SPS 6

Contains Virtual Data Model (VDM)

SAP HANA Live 1.0 for SAP ERP SPS 10

SAP Business Suite Product

SAP enhancement package 7 for SAP ERP 6.0 SPS 7

For more information about the system landscape to run SAP Smart Business cockpits, see Installation.

Component for Customer Incidents

  • PS-FIO