 Project Earned Value

 

The analytical app displays the Key Performance Indicator (KPI) Project Earned Value. You can drill down to view the earned value details of a project. The earned value is used to analyze the project performance and progress across projects.

Key Features

  • You can view the budgeted costs of work scheduled and performed, actual cost, cost and schedule variance of a project.

  • There are charts used to display the earned value and variance details for projects across periods for the current and previous fiscal year.

    Note Note

    For every fiscal year, only (01-12) periods are used to display the earned value.

    End of the note.
  • For a generic drill-down app, filter dimensions can be configured using the KPI Modeler. Additionally, you can configure the data representation to switch between a chart and tabular display.

  • Integration with the SAP Jam collaboration platform.

System Landscape Requirements

The app consists of front-end components and back-end components. The back-end components and the front-end components are delivered in separate products and have to be installed in a system landscape that is enabled for SAP Fiori.

SAP Smart Business Product

SAP Smart Business 1.0 for SAP ERP SPS 6

Contains Virtual Data Model (VDM)

SAP HANA Live 1.0 for SAP ERP SPS 10

SAP Business Suite Product

SAP enhancement package 7 for SAP ERP 6.0 SPS 7

For more information about the system landscape to run SAP Smart Business cockpits, see Installation.

Component for Customer Incidents

  • PS-FIO