Function documentationInternal Order Planning

 

Internal order planing to used to plan, collect, and settle the costs of internal jobs and tasks and involves planning for overhead cost orders, internal orders with revenues, accrual orders, and capital investment orders.

Prerequisites

You have installed SAP NetWeaver Business Client software.

You have made the settings in Customizing for Controlling under Start of the navigation path General Controlling Next navigation step Roles for NetWeaver Business Client End of the navigation path.

You have access to the following roles:

  • Internal Controller (SAP_CO_INTERNAL_CONTROLLER)

  • Cost Center Manger (SAP_CO_COSTCENTER_MANAGER)

You have activated the following:

Web Dynpro Application Configurations
  • Order Cost Element Planning (Basic) (FCOM_IP_ORD_COSTELEM01)

  • Order Cost Element Planning (Additional Features) (FCOM_IP_ORD_COSTELEM02)

  • Order Top Down Cost Element Group Planning (FCOM_IP_ORD_COSTELEM03)

  • Order Cost Element Planning (Multiple Currencies) (FCOM_IP_ORD_COSTELEM04)

  • Order Activity Input Planning (FCOM_IP_ORD_ACTINPUT01)

  • Order Activity Input Planning (Multiple Currencies) (FCOM_IP_ORD_ACTINPUT02)

  • Secondary Order Costs Planning (FCOM_IP_ORD_ACTINPUT03)

  • Secondary Order Costs Planning (Multiple Currencies) (FCOM_IP_ORD_ACTINPUT04)

Queries

You can remove or copy and extend the delivered queries to suit your requirements.

The following queries are delivered for cost element planning:

  • Order Primary Cost Element Planning by Fiscal Year Advanced (/ERP/COOM_A41_IRQ0001)

  • Order Revenue Element Planning by Fiscal Year Advanced (/ERP/COOM_A41_IRQ0002)

  • Order Secondary Cost Element Planning by Fiscal Year (/ERP/COOM_A41_IRQ0003)

  • Order Primary Cost Element Planning by Fiscal Year Simple (/ERP/COOM_A41_IRQ0011)

  • Order Revenue Element Planning by Fiscal Year Simple (/ERP/COOM_A41_IRQ0012)

  • Order Primary Cost Element Planning by Periods Advanced (/ERP/COOM_A42_IRQ0001)

  • Order Revenue Element Planning by Periods Advanced (/ERP/COOM_A42_IRQ0002)

  • Order Secondary Cost Element Planning by Periods (/ERP/COOM_A42_IRQ0003)

  • Order Primary Cost Element Planning by Periods Simple (/ERP/COOM_A42_IRQ0011)

  • Order Revenue Element Planning by Periods Simple (/ERP/COOM_A42_IRQ0012)

The following queries are delivered for activity input planning:

  • Order Activity Input Planning on Years (/ERP/COOM_A43_IRQ0001)

  • Order Activity Input Planning on Periods (/ERP/COOM_A44_IRQ0001)

The following queries are delivered for secondary order costs planning:

  • Order Secondary Order Costs Planning on Years (/ERP/COOM_A45_IRQ0001)

  • Order Secondary Order Costs Planning on Periods (/ERP/COOM_A46_IRQ0001)

The following queries are delivered for reporting on the plan data by comparison with the relevant reference data:

  • Order Cost Element Actual/Planning Comparison Costs/Revenue (/ERP/COOM_A42_Q0001)

  • Order Cost Element Actual/Planning Comparison (/ERP/COOM_A42_Q0002)

  • Order Cost Element Actual/Planning Comparison (/ERP/COOM_A42_Q0003)

  • Order Activity Input Planning Actual Comparison (/ERP/COOM_A44_Q0001)

  • Order Secondary Order Costs Planning Actual Comparison (/ERP/COOM_A46_Q0001)

Features

Internal order planning covers the following planning methods:

  • Activity input planning (detailed planning)

    Activity input planning allows you to plan by cost element such as material costs and activity input such as research activities to be supplied by the cost centers.

  • Primary costs and revenues planning

    You plan the primary costs and revenues by cost element. You can also plan on cost element groups and automatically distribute the costs to the assigned cost elements. For more information, see Planning Primary Costs and Revenues.