To be able to pack materials, you must first create an empty handling unit. In a second step, you can then assign materials to this handling unit; the materials are then packed.
In the
packing dialog
, select the
Pack material
or
Pack HUs
tab.
In the
All existing HUs (available for packing)
section, enter an allowed packaging material into the
Pack. matl
field (see also
Displaying allowed packaging materials
).
If you work with external identification numbers, enter these in the
Handling unit
field.
If you only enter one packaging material, the handling unit number is assigned internally according to the settings in Customizing.
Note
During packing within delivery processing, you can also enter a customer’s packaging material (in the outbound delivery) or a vendor‘s packaging material (in the inbound delivery) in the
CustPackMat.
field as an alternative to the packaging material.