Show TOC

 Allocation - Schedule Line with Goods Receipt

Technical name: 2LIS_02_SGR

Technical Data

Type of DataSource

Transaction Data (Movement Data)

Application Component

Materials Management (MM)

Available as of OLTP Release

SAP R/3 4.0B

Available as of Plug-In Release

PI 2002.1

RemoteCube Compatibility

No

Prerequisites

Activation of the DataSource.

Use

This DataSource is used to extract the schedule line quantities allocated with goods receipt quantities consistently to a BW system.

Delta Update

A delta update is supported. Delta process: ABR – Complete delta update with deletion indicator using delta queue (Cube-compatible).

Fields of Origin in the Extraction Structure

Field in Extraction Structure

Description of Field in Extraction Structure

Table of Origin

Field in Table of Origin

BWVORG

BW: Transaction Key SAP BW

hard-coded

EBELN

Document Number of Purchasing Document

EKET

EBELN

EBELP

Item Number of Purchasing Document

EKET

EBELP

SCLDT

Item Delivery Date

EKET

EINDT

SCLTM

Time of Delivery Date

EKET

UZEIT

SCLNR

Schedule Line Counter

EKET

ETENR

GMVPDT

Schedule Line Purchase Order Date

EKBE

BUDAT

BELNR

Number of Material Document

EKBE

BELNR

BUZEI

Item in Material Document

EKBE

BUZEI

SCLQTY

Schedule Line Quantity

EKET

MENGE

GMVQTY

Goods Movement Quantity

EKBE

MENGE

OPNQTY

Open Quantity

calculated

TTLQTY

Assigned Quantity

calculated

MEINS

Base Unit of Measure

EKPO

MEINS

ROCANCEL

Cancellation of Data Record

hard-coded

Features of Extractor

This DataSource provides information about the quantity of goods movements that were distributed to the schedule lines.

This means that the sequence of information in this DataSource is based on information in the schedule lines, but not on the information in the goods movement.

Because it is possible to post a goods receipt with a posting date (EKBE-BUDAT) that lies before or after the document creation date (EKBE-CPUDT), the creation date of the goods receipt document (GR document) plays an important role in the quantity distribution process.

The first GR document created is also the first document whose quantities are distributed, and this occurs irrespective of the posting date.

The information is only available in this DataSource if a goods movement was posted with respect to an order. Information about orders without goods receipt is not available.

In the Purchasing component in the SAP R/ 3 System, you will find data on goods movements in the table EKBE ( Purchasing Document History ), and data on schedule lines in the table EKET ( Scheduling Agreement Schedule Lines ).

To improve performance, this DataSource contains no information about scheduling agreements. This also applies to returns items, service items, and limit items.

For more information about purchasing documents, confirmations, and schedule lines, see the SAP Library under Start of the navigation path Materials Management Next navigation step Purchasing End of the navigation path .

Important Key Figures

SCLNR

Schedule line number in purchasing document

BELNR

Number of the material document used to post the goods movement

GMVPDT

Posting date of goods movement

SCLQTY

Schedule line quantity (quantity delivered by a vendor with regard to a schedule line)

GMVQTY

Quantity of a goods movement posted with respect to a schedule line

OPNQTY

Difference between the schedule line quantity (SCLQTY) and the total quantity (TTLQTY)

TTLQTY

Total quantity of goods movements posted for a schedule line

Example

Purchasing document 4500000001, Item 0010, has the following schedule lines:

Schedule line number (SCLNR) = 1

Delivery date (SCLDT)= 01.01.04

Delivery time (SCLTM) = 12:00:00

Quantity ordered(SCLQTY) = 20

A goods movement is posted with the following information:

Posting date (BUDAT) = 05.01.04

Document number of goods receipt (BELNR) = 5000000001

Item in document (BUZEI) = 1

Goods receipt quantity (MENGE) = 6

The DataSource results as follows:

ROCANCEL

'blank'

BWVORG

01

EBELN

4500000001

EBELP

0010

SCLDT

01.01.2004

SCLTM

12:00:00

SCLNR

1

GMVPDT

05.01.2004

BELNR

5000000001

BUZEI

0001

SCLQTY

15

GMVQTY

6

OPNQTY

9 => SCLQTY – TTLQTY => 15 -6

TTLQTY

6

MEINS

Base unit of measure of order

Data Review in SAP R/3

In the Purchasing component of SAP R/ 3 , you can use the General Reports transaction (transaction code ME80FN) to select, aggregate, and summarize information about purchasing activities. You can assemble the information that is to be reported according to selection criteria such as material, purchasing document, vendor, plant, and purchasing organization.

To assign the information in the list of issued purchasing documents clearly according to your wishes, you can use functions such as Sort, Filter, Aggregate Across Various Fields, Add Totals and Subtotals. You can also display the detail data for a purchasing document, a vendor, or a material.

Changing the View

If you select Change View , you can choose between the following views to display the output list:

  • Header/Item Data (data from the tables EKKO and EKPO)

  • Delivery Schedule Lines (data from the table EKET)

  • Purchase Order History (data from the table EKBE)

Setting the Layout

If you select Choose Layout , you have access to all the SAP List Viewers functions. In other words, you can change the existing layout (such as add or hide fields and columns, change the sort sequence, add subtotals, set filters), save the changed layout, and choose a different layout.

Comparing DataSource 2LIS_02_SGR to ME80FN

If you choose the Delivery Schedule Lines view in the transaction ME80FN, you can compare the data in the DataSource fields with the original document data in SAP R/3 , such as:

  • Purchasing Document Number (EBELN)

  • Item Number of Purchasing Document (EBELP)

  • Delivery Date (EINDT)

  • Schedule Line Quantity (SCLQTY)

You can check the information about the goods receipt in the Purchase Order History view.