The two methods which are available for calculating DSO are as follows:
The direct calculation of DSO is based on original documents. The period of time between posting date and clearing date of the financial document line item is calculated to provide accurate results.
The formulas for the direct calculation method are as follows:
Formulas for Direct Calculation Method
*The Reference Date for Net Due Receivable Calculation is either the Baseline Date for Due Date Calculation (table BSEG field ZFBDT) or the Document Date (table BKPF field BLDAT) if the Baseline Date is not filled.
With the indirect calculation method DSO is calculated on an aggregated level. Here the accounts receivable balance and revenues are taken into account to derive the measure on the DSO performance.
DSO can be calculated per month or for the entire selected timeframe. The calculation per month is used for those analysis steps that depict a development over time.
The formulas for indirect calculation per month are as follows:
Formulas for Indirect Calculation Method per Month
The formulas for indirect calculation overall (for the entire selected timeframe) are as follows:
Formulas for Indirect Calculation Method Overall