Once a task is scheduled, you can change its start time and date, or you can delete it.
Deleted tasks can be reactivated.
Go to the
To do
view.
Double-click the icon in the
Attributes
column.
A dialog box is displayed. A dialog box is displayed, showing attributes that were defined when the task was created.
Choose
Display <-> Change
.
Change the task start time and date in the
Task Scheduling
section.
Choose
Continue
and confirm your changes.
The task is now scheduled for the new time. It will be processed when the task processor job runs after the specified start time.
Go to the
To do
view.
Select the row of the task to be deleted.
Choose
Delete
.
The task is deactivated and moved to the
Deleted
view.
Deleted tasks can be reactivated. You may want to reactivate a deleted task if it was deleted by accident.
Go to the
Deleted
view.
Select the row of the task to be reactivated.
Choose
.A dialog box is displayed.
Confirm your entries.
The task is moved to the
To do
view. A reactivated icon will be displayed in the
Task icon
column. You may need to adjust the task date and time.