Specify the analysis project for which you are creating the analysis, and the time to start the analysis.
Note
If you start creating the analysis in the Analysis Project Overview, specify the analysis project there.
Open the input help for Analysis Project
and select an entry; this is not necessary if the analysis project has already been set.
Click the Name
field and give the analysis a name.
Open the input help for Scheduling Mode
and choose one of the following entries:
Immediately
, to start the analysis immediately after creation (default).
Scheduling
to set a start time for the analysis as follows:
Click in the Planned Start Date
field or open the corresponding entry help to specify a Date for starting the analysis.
Click in the Planned Start Time
field and enter a Time.