Function documentationUpload/Download project contents Locate this document in the navigation structure

 

You can prepare the following content for an existing project and upload it into the SAP system, with Microsoft Excel:

Prerequisites

The following prerequisites must be met:

  • The project must be created

  • Logical components must be created and assigned to the project

  • The project structure must be defined (for project structure attributes and contents of the tab pages)

Activities

Proceed as follows:

  1. Create the template file for the project structure

  2. Fill out the template file for the project structure

  3. Upload the project structure file

  4. Create the template files for the project structure attributes and/or related tab pages

  5. Fill out the template files for the project structure attributes and/or related tab pages

  6. Upload the template files for the project structure attributes and/or related tab pages

You have to carry out steps 1-3 first to create the project structure. You can carry out steps 4-6 optionally after steps 1-3 for the project structure attributes and/or tab pages.

Dependencies

Note the following dependencies when uploading the contents for the Test Cases and Transactions tab pages:

When you specify test objects on the Test Cases tab page, the system checks them against the existing entries on the Transactions tab page. This means that you have to upload the data for the Transactions tab page before you upload it for the Test Cases tab page.