Procedure documentationImporting Projects Locate this document in the navigation structure

 

You can import the transport requests of an entire project into a follow-on system of the system landscape.

Note Note

The number of transport requests imported depends on where you call the Import. You decide whether you want to import an entire project, or all transport requests of a change.

End of the note.

Procedure

  1. Select the project to be transported from the project overview screen.

  2. Choose Manage Transports and then the Import All Transport Requests option.

  3. A dialog box is displayed, in which you can enter the import parameters for the project.

  4. If necessary, change the logical target system into which the import is to be carried out.

  5. There are three tab pages in this dialog box:

    • Date: You can specify whether to import the data immediately or at a scheduled date and time. For more information, see Start Import: Time.

    • Execution: You specify whether to have a synchronous or an asynchronous import. For more information, see Import: Execution.

    • Options: You have several different options for importing, which you can select. These are explained in Import: Options.

  6. Enter the required parameters, and choose OK.

  7. The import runs immediately or is scheduled for the designated date and time.

Result

The transport requests of the project have been imported into the follow-on system.