You have assigned a cProjects project to a project cycle; however, you now want to assign it to a different one. First you must remove the current link between the project and the project cycle.
When you assign the project to a different project cycle, the phase and status of the project remain unchanged. This could cause inconsistencies in the phases between the project and the new project cycle
You have assigned a cProjects project to a project cycle.
1. Call transaction /TMWFLOW/MAINTINST.
2. Select the relevant tab page (Maintenance Cycles, Implementation Projects, Template Projects, or Upgrade Projects).
3. Open a task list by clicking it.
4. Choose Remove cProjects project from <project type>.